Project Details
Project Name: BankStar Financial Volga
Project start date: 06/21/23
General Contractor: Clark-Drew Construction
Owner: BankStar Financial
Visual production by Vertical Vision LLC
____________________________________________________________
Project Progression
June 21, 2023 – Pre-construction
July 23, 2023 – Groundbreaking
August 7, 2023 – Footings / Rebar
August 20, 2023 – Poured Foundation with Forms
August 27, 2023 – Foundation without Forms
September 8, 2023 – Partial Backfill and Beams
September 15, 2023 – Completed Backfill and Beams
October 15, 2023 – Framing and Roof
October 22, 2023 – Exterior Work and Framing
October 29, 2023 – Roof, Final Framing, Basement
November 4, 2023 – Finalize Roof, Rough In
November 12, 2023 – Final Rough In, Parking Lot Prep
November 28, 2023 – Insulation, Mech Rough-In, Windows
December 10, 2023 – Sheetrock, Main Electrical Panel
December 23, 2023 – Final Interior Rough In
January 4, 2024 – Taping, HVAC, Brick Facade
January 26, 2024 – Paint, Electrical, Brick Facade
February 12, 2024 – Brick Facade, HVAC
February 26, 2024 – Cabinets, Lighting
March 12, 2024 – Brick Facade, Cabinets, Electrical
April 4, 2024 – Cabinets, Flooring
Aerial photos showing progress
Photos taken over the course of the project. No aerial flight on Jan 26. FAA flight ceiling too low.
Ortho photos showing progress
Photos taken over the course of the project. No aerial flight on Jan 26th or May 21st.
Videos
Video of the future construction site of BankStar Financial in Volga, SD.