Project Details
Project Name: BankStar of Elkton
Project start date: August of 2023
General Contractor: Clark Drew Construction
Owner: BankStar Financial
Architect: Perspective Inc
Visual production by Vertical Vision LLC
____________________________________________________________
Construction Progression
June 21, 2023 – Pre-construction
August 23, 2023 – Demolition Day
September 30, 2023 – Basement Walls
October 7, 2023 – Partial Backfill
October 29, 2023 – Basement Slab
November 4, 2023 – Steel Erection (partial)
November 12, 2023 – Cap, Steel Erection
November 29, 2023 – Final Framing
December 7, 2023 – Final Roofing
December 23, 2023 – Interior Rough In
January 18, 2024 – Electrical/HVAC Rough In
January 31, 2024 – Insulation, Sheetrock
February 12, 2024 – Taping, HVAC
February 26, 2024 – Primer, HVAC
March 11, 2024 – Paint, Ceilings
April 4, 2024 – Exterior Brick, Cabinets

Aerial photos showing progress
Photos taken over the course of the project. No update for January 18, 2024.
Aerial photos before demolition
Photos taken on July 7, 2023
Video of Bankstar
Video of BankStar Financial in Elkton, SD prior to demolition.