Project Details
Project Name: Flandreau Fire Station
Project start date: June, 2023
General Contractor: WS Construction
Owner: City of Flandreau, SD
Visual production by Vertical Vision LLC
____________________________________________________________
Project Progression
June 12, 2023 – Pre-construction
July 26, 2023 – Groundbreaking
August 8, 2023 – Foundation forms and footings
August 20, 2023 – Backfilled Foundation
August 27, 2023 – Plumbing rough in
September 6, 2023 – Steel Erection
September 13, 2023 – Finished Steel Erection
September 30, 2023 – Exterior Siding and Framework
October 15, 2023 – Roofing and Interior Walls
October 21, 2023 – Pre-stress Roof
October 29, 2023 – Grading, Interior, Concrete Floor Prep
November 4, 2023 – Concrete Slab (Partial)
November 12, 2023 – Slab, Sidewalks and Stoops
November 17, 2023 – Curb, Driveway, Final Roofing
November 29, 2023 – Final Concrete, Rough-In, Sidewalks
December 7, 2023 – Mech Rough-In, Sidewalks
December 23, 2023 – Doors, Sheetrock, HVAC
January 9, 2024 – HVAC, Windows/Doors
January 31, 2024 – Electrical, HVAC
February 21, 2024 – Electrical Rough-In
March 13, 2024 – Paint, Landscaping, Water Lines
April 4, 2024, – Tile, Doors, Cabinets



Aerial photos showing progress
Photos taken over the course of the project. No update for January 18.
Photos showing progress
Photos taken over the course of the project. No update for January 18.