BankStar Volga Foundation Verification

Bankstar Volga

Foundation Verification

Foundation is visually checked to verify that nothing has shifted or moved after the forms are set. Foundation is visually verified after the footings are poured, then after the forms are removed and finally after the foundation is backfilled.

The red outline is the original placement of the footing forms.

Floorpoan without RED border1 Floorpoan with RED border1

The overlay used to for verification is derived from the actual floorplans.

Aug 20 without Red overlay Aug 20 with Red overlay

Verified after the foundation is poured as of August 20, 2023.

Aug 27 without RED overlay Aug 27 with RED overlay

Verified after the forms are removed on August 27, 2023.

Sept 8 without RED overlay Sept 8 with RED overlay

Verification after the foundation walls are partially backfilled and before steel re-enforcement beams are installed as of September 8, 2023.

Sept 15 without RED overlay Sept 15 with RED overlay

Final verification after the foundation walls are completely backfilled as of September 15, 2023.

Ortho 2 Before Oct 7 Ortho 2 After Oct 7

Final verification after the main level slab was poured as of September 23, 2023.

Conclusion:

Visual comparison to the original footing form placement after each phase of the the foundation and walls show no signs of movement.